N2 - In the container terminals of seaports, the container handling system consists of a variety of container handling machines such as quay cranes, internal yard trucks, and yard cranes. This study applies a holistic approach to the integrated scheduling of these machines for the container handling operations of a single vessel. We formulate this special hybrid flow shop scheduling problem through both mixed integer programming (MIP) and constraint programming (CP) techniques. Then we develop an easily-implemented approach that combines the strengths of MIP and CP. First, the MIP model, which only considers quay crane scheduling, is solved by an MIP solver, and a quay crane allocation plan is retrieved from the MIP solution. Then, this quay crane allocation plan is fed to the CP model, warm-starting the branch-and-prune algorithm built in a CP optimizer. Our numerical experiments reveal that this hybrid MIP/CP approach can solve the large-sized instances with up to 1000 containers, 6 quay cranes, 36 yard trucks, and 15 yard cranes to optimality with a gap of less than 3.31%, within a solution time of 2 minutes. If we increase the solution time to 5 minutes, this hybrid approach solves larger instances with up to 1400 containers to optimality with a gap of less than 1.41%. The state-of-the-art dedicated algorithms reported in the literature (which address an easier version of the same problem by ignoring non-crossing constraints and safety margins between quay cranes) are only able to find solutions for real-life instances with up to 500 containers within the solution time of 2930 or 5221 seconds, leaving a 4% or an unknown optimality gap. Thus, this study improves the solution of this integrated scheduling problem in terms of the instance size, solution efficiency, and solution optimality.
AB - In the container terminals of seaports, the container handling system consists of a variety of container handling machines such as quay cranes, internal yard trucks, and yard cranes. This study applies a holistic approach to the integrated scheduling of these machines for the container handling operations of a single vessel. We formulate this special hybrid flow shop scheduling problem through both mixed integer programming (MIP) and constraint programming (CP) techniques. Then we develop an easily-implemented approach that combines the strengths of MIP and CP. First, the MIP model, which only considers quay crane scheduling, is solved by an MIP solver, and a quay crane allocation plan is retrieved from the MIP solution. Then, this quay crane allocation plan is fed to the CP model, warm-starting the branch-and-prune algorithm built in a CP optimizer. Our numerical experiments reveal that this hybrid MIP/CP approach can solve the large-sized instances with up to 1000 containers, 6 quay cranes, 36 yard trucks, and 15 yard cranes to optimality with a gap of less than 3.31%, within a solution time of 2 minutes. If we increase the solution time to 5 minutes, this hybrid approach solves larger instances with up to 1400 containers to optimality with a gap of less than 1.41%. The state-of-the-art dedicated algorithms reported in the literature (which address an easier version of the same problem by ignoring non-crossing constraints and safety margins between quay cranes) are only able to find solutions for real-life instances with up to 500 containers within the solution time of 2930 or 5221 seconds, leaving a 4% or an unknown optimality gap. Thus, this study improves the solution of this integrated scheduling problem in terms of the instance size, solution efficiency, and solution optimality.
KW - Constraint programming
KW - Container terminal
KW - Container unloading/loading problem
KW - Mixed integer programming
KW - OR in maritime industry
UR - http://www.scopus.com/inward/record.url?scp=85081314508&partnerID=8YFLogxK
U2 - 10.1016/j.ejor.2020.02.021
DO - 10.1016/j.ejor.2020.02.021
M3 - Article
AN - SCOPUS:85081314508
SN - 0377-2217
VL - 285
SP - 884
EP - 901
JO - European Journal of Operational Research
JF - European Journal of Operational Research
IS - 3
ER -