N2 - Chinese Architecture, Engineering, Construction (AEC) industry is under the reform resulting from the large amount of waste production, huge energy consumption and severe environmental pollution. Aiming to maximize the project value while reducing the waste and cost, lean thinking is referred from manufacturing industry to construction since two industries have several similarities. This paper reviewed the change of lean thinking from production to construction, the differences between traditional and lean construction (LC), and the current situation of Chinese LC situation. Besides, a case study was assessed to examine how the LC management works in a practical project in China. Through the research, project schedule is divided into several hundred sub-items to assist the site supervisors to manage the construction progress. In addition, utilizing prefabrication parts and digital technology are two effective approaches to conduct the LC in the project.
AB - Chinese Architecture, Engineering, Construction (AEC) industry is under the reform resulting from the large amount of waste production, huge energy consumption and severe environmental pollution. Aiming to maximize the project value while reducing the waste and cost, lean thinking is referred from manufacturing industry to construction since two industries have several similarities. This paper reviewed the change of lean thinking from production to construction, the differences between traditional and lean construction (LC), and the current situation of Chinese LC situation. Besides, a case study was assessed to examine how the LC management works in a practical project in China. Through the research, project schedule is divided into several hundred sub-items to assist the site supervisors to manage the construction progress. In addition, utilizing prefabrication parts and digital technology are two effective approaches to conduct the LC in the project.
UR - http://www.scopus.com/inward/record.url?scp=85108920063&partnerID=8YFLogxK
U2 - 10.1201/9781003000716-50
DO - 10.1201/9781003000716-50
M3 - Conference Proceeding
AN - SCOPUS:85108920063
SN - 9780367430191
T3 - Sustainable Buildings and Structures: Building a Sustainable Tomorrow - Proceedings of the 2nd International Conference in Sustainable Buildings and Structures, ICSBS 2019
SP - 365
EP - 370
BT - Sustainable Buildings and Structures
A2 - Papadikis, Konstantinos
A2 - Chin, Chee S.
A2 - Galobardes, Isaac
A2 - Gong, Guobin
A2 - Guo, Fangyu
PB - CRC Press/Balkema
Y2 - 25 October 2019 through 27 October 2019
ER -